PROJECTS SO FAR WITH COMPLETION RATES AND TIMELINES

Kisii Sunrise
previous arrow
next arrow
Slider

FIRE STATION. 1 Construction and Completion of Fire Station. 75% 6 29-Aug-2019
URBAN ROADS AND WALKWAYS.
1 Construction and Completion Construction of BLACKHOUSE – CATHEDRAL – MWEMBE SDA- ETANGI. 31% 3 7-Jun-2019
2 Construction and Completion of FIRE STATION – STORM HOTEL ROAD. 95% 3 7-Jun-2019
3 Construction and Completion of access road to NEW DARAJA MBILI MARKET. 68% 3 7-Jun-2019
4 Construction and Completion of GALILAYA – LOMA ACADEMY JUNCTION ROAD. 98% 3 7-Jun-2019
5 Rehabilitation of BOSONGO – BOTORI ROAD. 73% 3 7-Jun-2019
6 Construction and Completion of SOKO MJINGA – GENESIS PRI – KISII EYE HOSPITAL ROAD. 79% 3 7-Jun-2019
7 Construction and Completion NATIONAL BANK – ST JUDE. 99% 3 7-Jun-2019
8 Construction and Completion BANK OF AFRICA- GOLF HOUSE. 80% 3 7-Jun-2019
9 Construction and Completion MASHAURI JUNCTION – KISII UNIVERSITY JUNCTION(ALONG KISII- KILGORIS ROAD). 58% 3 7-Jun-2019
STORM WATER DRAIN. 1 Construction and Completion KISII PRISONS BOX CULVERT ALONG RIVER NYAKOMISARO. 99% 4 7-Jul-2019
2 Construction and Completion of BRIDGE INTERNATIONAL SCH – CATHEDRAL RD DRAIN. 100% 3 7-Jun-2019
3 Construction and Completion NATIONAL CEREALS AND PRODUCE BOARD- DARAJA MBILI BY PASS. 99% 3 7-Jun-2019
4 protection works for drain at YWCA – DOWNSTREAM. 47% 3 7-Jun-2019
5 protection works for drain behind UMOJA BUILDING – DOWNSTREAM. 93% 3 7-Jun-2019
6 Construction and Completion of BLACKHOUSE – GUSII HIGHLIGHTS DRAIN. 74% 3 7-Jun-2019